Gander Builders Custom Home Timeline
Lot Selection and Purchase
Proper Selection vs. Home Size
4 weeks or more
Purchase Negotiation / Contract Signing
2 to 4 weeks or more
Financing
2 to 4 weeks or more
Working Drawings
Specification Review and Amending
2 weeks or more
Preliminary Phase
2 weeks or more
Drawing Phase
4 weeks or more
This phase of construction can vary by the amount of time you actually spend with the architect. Anywhere from a minimum of five weeks to over a year.
Engineering
Spot Home On Lot With All Topos
1 week
Village Approval
2 weeks
This phase is dependent on which days of the week the meetings take place, how often each month the Village meet and whether or not the home meets their approval the first time around (if it fails you will need to go back to the architect, which will need to fit it into his schedule to revise).
County Septic Approval
Village Septic Approval
2 to 3 weeks
Well Application / Approval
2 to 3 weeks
Septic Application / Approval
4 to 6 weeks
Building Permit
Application Submitted
1 week
Preliminary Review
2 to 3 weeks
Village Engineering Review
2 to 3 weeks
Final Review
1 to 2 weeks
This phase can vary depending on the prospects of passing during the preliminary review. If it does not (which is the norm), the plans must go back to the architect for revisions (which is dependent on his schedule).
Obtaining A Building Permit
Total Time Required to Aquire Permit
Give or take 3 - 5 months
Building Process
Total Time Required to Build A Home
5 - 6 months
Fall Through Spring
6 months or more