Lot Selection and Purchase |
|
|---|---|
Proper Selection vs. Home Size |
4 weeks or more |
Purchase Negotiation / Contract Signing |
2 to 4 weeks or more |
Financing |
2 to 4 weeks or more |
Working Drawings |
|
|---|---|
Specification Review and Amending |
2 weeks or more |
Preliminary Phase |
2 weeks or more |
Drawing Phase |
4 weeks or more |
| This phase of construction can vary by the amount of time you actually spend with the architect. Anywhere from a minimum of five weeks to over a year. | |
Engineering |
|
|---|---|
Spot Home On Lot With All Topos |
1 week |
Village Approval |
2 weeks |
| This phase is dependent on which days of the week the meetings take place, how often each month the Village meet and whether or not the home meets their approval the first time around (if it fails you will need to go back to the architect, which will need to fit it into his schedule to revise). | |
County Septic Approval |
|
|---|---|
Village Septic Approval |
2 to 3 weeks |
Well Application / Approval |
2 to 3 weeks |
Septic Application / Approval |
4 to 6 weeks |
Building Permit |
|
|---|---|
Application Submitted |
1 week |
Preliminary Review |
2 to 3 weeks |
Village Engineering Review |
2 to 3 weeks |
Final Review |
1 to 2 weeks |
| This phase can vary depending on the prospects of passing during the preliminary review. If it does not (which is the norm), the plans must go back to the architect for revisions (which is dependent on his schedule). | |
Obtaining A Building Permit |
|
|---|---|
Total Time Required to Aquire Permit |
Give or take 3 - 5 months |
Building Process |
|
|---|---|
Total Time Required to Build A Home |
5 - 6 months |
Fall Through Spring |
6 months or more |